Hi Ram,

 

The number range settings which we maintain in OMI2 is for planned orders which are created by MRP run. But in my case, the MRP will be executed in APO. So i feel that i need NOT to maintain number range in OMI2. I feel i need to maintain number range in OMI3 (manually created planned orders).

 

My question is:

 

In OMI3, should i maintain the number range as "External or Internal"? The number range which i maintain in OMI3 should be same as which i have maintained in APO number range?

 