Hi All,
We have requirement to allow creation of planned order manually if production version is valid on order start date and not finish date. This is because lead time of order is longer. I refered OSS notes 385602. I could find out solution for this is implementation of OSS note 694140 to change validity mode at activity level to consider start date of first produce activity in validity interval. Problem is even If I create order in APO by implementiong this note planned order is not transfered to ECC and it gets stuck with error production version not valid.
Is there any way in ECC to control this? Any config or customization?
Regards,
Santosh