Re: CHARM Normal Change Project Cycle empty

$
0
0

Hi Rishav/All,

 

Table shows project is active. We will try to withdraw this normal change and create a new one. Problem is not with selecting the project but it is regarding the Project Cycle and Current phase fields in the normal change form not getting auto populated.

 

SOLAR_PROJECT_ADMIN has same task list and display cycle. I checked lot of sdn and sap notes but could not figure out this issue.

 

Regards,

Salman